Determination of the common man-caused clay deposit parameters in the internal pit dump
DOI:
https://doi.org/10.33271/crpnmu/63.007Keywords:
surface mining, pit, common man-caused deposit, clay, dump, accompany raw materials.Abstract
Purpose. Substantiation of the efficient parameters of a common man-caused clay deposit on the territory of the pit internal dump at the surface mining of placer deposits. Research methodology. The analytical research method was used to determine the main parameters of a common man-caused clay deposit in the pit internal dump, taking into account the thickness of the stored layer of raw materials. The graphical research method was used to determine the most efficient thickness of a common man-caused deposit in the pit internal dump during the surface mining of placer deposit. The results. It has been confirmed that with an increase of the section length of a man-caused deposit from 100 to 400 m, its actual area increases by 16% from 52 to 63 hectares, while the volume of the dams construction works decreases in 1.6 times from 10.3 to 6.7 million m3. The established parameters of common man-caused deposits during the development of placer deposits make it possible to assert that, in relation to the volume of work on the dams construction, the most efficient is a man-caused deposit with a thickness of 10 m, but its submission will lead to a 2.2 times increase of the area of land required for the placement of accompany raw materials in comparison with man-caused deposit with a thickness of 20 m. Scientific novelty. Dependences of the thickness and area of man-caused deposit on its width during the pit internal dump formation have been established. The dependences of the actual area of man-caused deposit and the work volume of the dams construction on the length of its section with accompany raw materials for man-caused deposits with a thickness of 10 and 20 m are determined. Practical value. The effective parameters of a common man-caused deposit have been determined depending on its capacity and the volume of accompany raw materials that are placed in it. A method for establishing the required number of common man-cause deposit sections, determining the work volume of the dams construction and the actual area of common man-caused deposit in the pit internal dump has been developed.References
Dychkovskyi, R., Vladyko, O., Maltsev, D., & Cáceres Cabana, E. (2018). Some aspects of the compatibility of mineral mining technologies. Rudarsko-Geološko-Naftni Zbornik , 33 (4), 73–82. https://doi.org/10.17794/rgn.2018.4.7
Ложніков, О. В., & Дичковский, Р. О. (2020). Встановлення параметрів багатосекційного складу глин у внутрішньому відвалі кар’єру при комплексній розробці розсипних родовищ. Геотехнічна Механіка , 152 , 263–274. https://doi.org/10.15407/geotm2020.152.263
Koner, R., & Chakravarty, D. (2016). Characterisation of overburden dump materials: a case study from the Wardha valley coal field. Bulletin of Engineering Geology and the Environment , 75 (3), 1311–1323. https://doi.org/10.1007/s10064-015-0830-x
Adamczyk, J., Cała, M., Flisiak, J., Kolano, M., & Kowalski, M. (2013). Slope stability analysis of waste dump in sandstone open pit Osielec. Studia Geotechnica et Mechanica , 35 (1), 3–17. https://doi.org/10.2478/sgem-2013-0001
Poulsen, B., Khanal, M., Rao, A. M., Adhikary, D., & Balusu, R. (2014). Mine Overburden Dump Failure: A Case Study. Geotechnical and Geological Engineering , 32 (2), 297–309. https://doi.org/10.1007/s10706-013-9714-7
Chang, L. S., Yang, T. Y., & Deng, H. J. (2013). Disaster Prediction and Preventive Measures of Constructing a Waste Dump on an Abandoned Tailing Pond. Applied Mechanics and Materials , 405 – 408 , 2427–2430. https://doi.org/10.4028/www.scientific.net/AMM.405-408.2427
Wang, Z., Lv, X., & Wang, J. (2012). Stability analysis of water-filled dump slope under the couple effect of seepage and damage. Disaster Advances , 5 (4) , 816–821. http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.658.2048&rep=rep1&type=pdf
Pipatpongsa, T., Khosravi, M. H., & Takemura, J. (2013). Physical modeling of arch action in undercut slopes with actual engineering practice to Mae Moh open-pit mine of Thailand. Proceedings of the 18th International Conference on Soil Mechanics and Geotechnical Engineer-Ing (ICSMGE18) , 943–946. https://www.cfms-sols.org/sites/default/files/Actes/943-946.pdf
Engel, J., Mihok, J., Rybar, R., & Tyulenev, M. (2018). Defining the Main Parameters of Hydro-Dumping at Open Pits. E3S Web of Conferences , 41 , 01004. https://doi.org/10.1051/e3sconf/20184101004
Downloads
Published
Issue
Section
License
All articles are published under the Creative Commons Attribution License (CC BY 4.0), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Authors retain copyright and grant the journal right of first publication.
Authors are permitted and encouraged to deposit the final published version of their article, or the Author's Accepted Manuscript (AAM), in institutional or subject-specific open-access repositories (including the university's own institutional repository, CORE, Zenodo, or Figshare), ensuring maximum visibility, accessibility, and impact of the publication.