Spatial optimization of the development workings system based on a three-dimensional geological-mathematical model under the conditions of the mine “Samarska”

Authors

DOI:

https://doi.org/10.33271/crpnmu/86.129

Keywords:

geological-mathematical model, three-dimensional geological modelling, spatial optimization, devel-opment workings, multi-criteria optimization, TIN models, mining suitability

Abstract

Purpose. The purpose of this study is to develop the theoretical foundations and a methodological framework for the spatial optimization of development workings based on a three-dimensional geological-mathematical model of the с5 coal seam under the conditions of the Samarska Mine (PJSC DTEK Pavlohradvuhillia), integrating three-dimensional geological modeling with multi-criteria optimization methods.

The methods. The research was conducted using three-dimensional geological modeling, TIN-based approximation of the coal seam roof and floor surfaces, spatial analysis of mining-geological parameters, construction of an integrated mining suitability index, and multi-criteria optimization of development workings trajectories.

Findings. A three-dimensional geological model of the c5 coal seam under the conditions of the Samarska Mine was developed, and the spatial distribution of seam thickness was analysed, revealing variations from 0.63 to 1.21 m. Thirteen extraction panels were delineated, with total recoverable reserves of 2.52 × 10⁶ m³. The parameters of the development workings for each panel were determined. The results indicate that the length of the development workings increases along the strike of the seam from 910 to 1457 m, whereas the overall seam dip decreases from 3.14° to 2.15°. The analysis demonstrates that the central part of the mine field provides the most favourable conditions for roadway development, exhibiting a balanced combination of roadway length, elevation difference, and permissible gradients.

The originality. A pattern of changes in the parameters of a mine field's reserve development system was established depending on the spatial correlation between mining suitability and mining-geological risk. It was demonstrated that a change in the integral seam development index (I=G−R) from 0.79 to 0.78 is accompanied by a nearly linear increase in the length of extraction pillars from 910 to 1,457 m and a simultaneous decrease in the maximum deviation angle of the development workings from 6.09° to 3.8° of the development system parameters.

Practical implications. The proposed approach enables the rational determination of mine development system parameters, adapts the layout of development workings to the spatial heterogeneity of the coal seam, and improves the efficiency of mine planning.

References

1. Malashkevych, D. S., Ruskykh, V. V., Medianyk, V. Yu., & Haidai, O. A. (2025). Prediction of coal seam occurrence using numerical methods and a three-dimensional geoinformation system. Naukovyi Visnyk Natsionalnoho Hirnychoho Universytetu, 5, 5–13. https://doi.org/10.33271/nvngu/2025-5/005

2. Руських, В. В., & Сулаєв, В. І. (2023). Методика прогнозування якісних показників вугілля в межах виїмкового стовпа. Збірник наукових праць НГУ, 73, 45–55. https://doi.org/10.33271/crpnmu/73.045

3. Haidai, O., Ruskykh, V., Ulanova, N., Prykhodko, V., Cáceres Cabana, E., Dychkovskyi, R., Howaniec, N., & Smolinski, A. (2022). Mine field preparation and coal mining in Western Donbas: Energy security of Ukraine – A case study. Energies, 15(13), Article 4653. https://doi.org/10.3390/en15134653

4. Dychkovskyi, R., Falshtynskyi, V., Ruskykh, V., Cáceres Cabana, E., & Kosobokov, O. (2018). A modern vision of simulation modelling in mining and near mining activity. E3S Web of Conferences, 60, Article 00014. https://doi.org/10.1051/e3sconf/20186000014

5. Journel, A. G., & Huijbregts, C. J. (1978). Mining geostatistics. Academic Press.

6. Houlding, S. W. (1996). 3D geoscience modeling: Computer techniques for geological characterization. Springer. https://doi.org/10.1016/0012-8252(95)00067-4

7. Mallet, J. L. (2003). Geomodeling. Oxford University Press. https://doi.org/10.1016/S0098-3004(03)00062-1

8. Cherep, A., & Russkykh, V. (2025). Justification of the technological scheme for the development of manganese ore as a critical raw material at the open pit completion. Advances in Science and Technology, 172, 3–18. https://doi.org/10.4028/p-3h0Alr

9. Wellmann, F., Caumon, G., & Schmelzbach, C. (2018). 3-D structural geological models: Concepts, methods, and uncertainties. Advances in Geophysics, 59, 1–121. https://doi.org/10.1016/bs.agph.2018.09.001

10. Deng, H., Zheng, Y., Chen, J., Yu, S., Xiao, K., & Mao, X. (2022). Learning 3D mineral prospectivity from 3D geological models using convolutional neural networks: Application to a structure-controlled hydrothermal gold deposit. Natural Resources Research, 31, 1899–1918. https://doi.org/10.48550/arXiv.2109.00756

11. Saaty, T. L., & Vargas, L. G. (2012). Models, methods, concepts & applications of the analytic hierarchy process (2nd ed.). Springer. https://doi.org/10.1007/978-1-4614-3597-6

12. Draper, N. R., & Smith, H. (1998). Applied regression analysis (3rd ed.). Wiley. https://doi.org/10.1002/9781118625590.ch15

Published

2026-09-30

Issue

Section

MINING AND OIL AND GAS TECHNOLOGIES